Replace Hoist and Monorail System, Building 3234

  • Location: Tinker AFB, OK
  • Customer: USACE
  • Project Cost: $5M

ASSET served as prime contractor to replace the existing monorail track, trolley duct, hoist trains and controls with newly constructed, reinforced structural framing to support a 20-ton capacity hoist system. To work around facility issues, ASSET developed an alternate construction option and successfully reconfigured the mechanical and structural requirements of the project.

A well-maintained and organized on-site material storage helped prevent delays and project down time. All materials were inspected upon delivery and at the time of installation to ensure quality products were being used. Record-keeping and document tracking was utilized to avoid potential problems with warranty items.

ASSET self-performed 84% of the work. The project was completed with zero safety incidents.